Central Water Line Construction Update

September 2026

An excavator works on Cherry Avenue
Crews excavate a trench on Cherry Avenue to make way for the new water line.
The Central Water Line Project continues to make steady progress as crews advance through portions of Stages 2, 3, 4, and 5 and prepare for several important upcoming construction activities. In this update, we'll highlight recent progress along the project corridor, including work on JPA, Cleveland Avenue, and Cherry Avenue, the unique challenges of installing pipe deep beneath the roadway, and upcoming work at the railroad crossing just south of Lewis Street.
Project at a Glance
5,426
feet of 30" ductile iron pipe installed

12
feet of 24" ductile iron pipe installed
281
feet of 8" ductile iron pipe installed (City)

240
feet of 2" cross-linked polyethylene pipe installed (City)

Jefferson Park Avenue

Stage 2

With Stage 1 work nearing completion last spring, crews moved into the southbound lane of Jefferson Park Avenue (JPA) and worked through early July. During the relatively small construction window, they were able to install 100% of the new 30" pipe, reaching the JPA and Cleveland Avenue intersection. Upon completion, the crew shifted over to Cherry Avenue to begin pipe installation work in front of Tall Oaks Elementary School while students were out on summer break.
Now that school is back in session, crews plan to return to JPA to work on permanent utility bedding. This work will require exposing gas laterals and backfilling them with rock dust. 

Installing Pipe Under the Railroad Tracks

Lewis Street and JPA

Within the next few weeks, work is expected to begin on the long-anticipated railroad crossing just south of Lewis Street.

Since active railroad tracks cannot be easily crossed with typical open cut water line installations, crews will employ a specialized trenchless construction technique. They will excavate a pit on each side of the tracks, enabling a 54-inch casing pipe to be bored beneath the tracks with specialized tunneling/auger equipment. The launch pit at the end of Lewis Street is expected to measure approximately 41 feet long by 16 feet wide and reach a depth of 30 feet. The receiving pit on the south side of the tracks is expected to measure approximately 16 feet long by 14 feet wide and reach a depth of approximately 30 feet.  Once the casing pipe is in place, the 30-inch ductile iron water line will slide through the casing and connect to the water lines on each side of the railroad.

This approach minimizes impacts to rail operations and allows trains to continue passing through the area while construction is underway.

To assist with the work, a railroad flagger will typically be on site to coordinate construction activities and halt work when a train approaches. In some cases, trains may need to reduce their speed while passing through the work area. Once the train has safely passed, construction activities can resume.

Cherry Avenue

Taking Advantage of the Summer Months

As previously mentioned, the crew working on JPA temporarily shifted over to Cherry Avenue in July to assist with construction work in front of Tall Oaks Elementary School. We were also fortunate to welcome a second pipe crew that began work on Cherry Avenue near the entrance of Charlottesville Middle School. 

Moving crews to Cherry Avenue allowed construction activities to take place in front of schools while students were out on summer vacation. Minimizing disruptions in the community is, and continues to be, a priority of this project and completing this vital work during the summer months helped alleviate potential traffic congestion issues. We are happy to report that crews were able to complete 200 feet of pipe installation on either side of the school entrances before the school year kicked off on August 12.

To keep the momentum going, both crews continued to work westward on Cherry Avenue completing a significant run of pipe. The crew currently working between Charlottesville Middle School and Tall Oaks Elementary School will continue progress in Cherry Avenue over the next few months. 

Cleveland Avenue

City Water Line Work

Work has commenced on Cleveland Avenue, with efforts now centered around installing an 8" ductile iron pipe for the City. The 30" Central Water Line will generally parallel the 8" water line beneath the roadway. Traffic flagging operations are expected to last for the duration of work on Cleveland Ave. 

What happens if Crews Encounter Rock?

Excavating can present some unique challenges, particularly if crews encounter rock below the roadway. 

If rock is encountered, specialized drilling equipment can be used to break the rock apart so it can be safely removed. One potential approach uses a “honeycomb” drilling pattern, where a series of strategically placed holes are drilled into the rock. These holes weaken the rock, allowing it to be broken apart and excavated more efficiently. In certain circumstances, crews may also use a specialized expansion grout. The grout is placed into drilled holes and expands, creating pressure within the rock and causing it to fracture.

These techniques are particularly useful when traditional rock blasting is restricted or impractical. Since the City of Charlottesville bans rock blasting within its boundaries without City Council approval, these alternative methods will be used.

Keeping the Project Moving

The Central Water Line is a large and complex project that requires crews to work around existing utilities, roadways, schools, businesses, railroad infrastructure, and other community needs. Each stage requires careful planning and coordination to keep construction moving while maintaining safe conditions for workers and the public. Current efforts will prioritize completing Stages 1-5 before moving east to Stages 6, 7, 8, and 9. 
We continue to appreciate the community's patience and understanding as this important investment in our water infrastructure progresses. The project is expected to be completed by December 2029.
Questions? Feel free to email us at CentralWaterLine@rivanna.org. Want to learn more about the Central Water Line Project?
Visit our construction webpage!

Central Water Line Project is One of Several Initiatives Planned

In 2002, the Central Virginia Region experienced a historical drought of record. This drought and the water supply needs of the Charlottesville/Albemarle region sparked a decade-long water supply planning process (2002-2012). Over the next four years, RWSA will invest more than $300 million to enhance our urban raw water storage capabilities, raw water transmission pipelines, treatment facilities, and finished water transmission pipelines (treated drinking water).
  1. New Earthen Dam – In 2014, RWSA completed building a new dam at the Ragged Mountain Reservoir. 
  2. Water Treatment Plant Improvements - Recent facility renovations and upgrades have increased treatment capacity. 
  3. Ragged Mountain Reservoir Pool Fill Project - RWSA will fully utilize the reservoir’s storage capacity by adding 700 million gallons of water for a total capacity of 2.1 billion gallons. 
  4. Ragged Mountain Reservoir to Observatory Water Treatment Plant Raw Water Line and Pump Station - A new 36” transmission pipe is replacing two smaller 70 and 100-year-old transmission pipes. 
  5. South Rivanna River Crossing - A large 24” finished water transmission pipe is being added to better support the northern area in Albemarle County. 
  6. Central Water Line - The Central Water Line will provide a high-flow, large-diameter finished water transmission pipe that will better connect RWSA’s treatment facilities, transmission pipes, water storage tanks, and water distribution piping in the urban area.  
  7. South Fork Rivanna Reservoir to Ragged Mountain Reservoir Raw Water Pipeline, Pump Station, and Intake - The new pipeline and pump station will allow RWSA to fully utilize the South Fork Rivanna Reservoir’s watershed and Ragged Mountain Reservoir’s storage capacity. It will also allow both water treatment plants to pull water from either reservoir. 