Central Water Line Construction Updates |
Sagres Construction continues to make steady progress on the Central Water Line Project. So far, the team has installed just over 600 feet of 30-inch pipe. In this e-newsletter, we will share details about upcoming work near UVA and offer a brief overview of activities you may notice as construction progresses.
|
New pipe is installed along Lewis Street.
|
UVA Work over the Holiday Break |
Beginning next week, construction crews will shift their focus to Stadium Road and Hereford Drive. Aimed to minimize disruptions, the work will occur while students are off for the holidays. To accelerate efforts, weekend work is planned for 12/27, 12/28, 1/3, and 1/4. During this time, you may notice flagging operations and occasional temporary closures.
|
Construction sites are active environments where many tasks occur. A passerby may notice workers, equipment, materials, and changing conditions as the project moves forward. Each visible element plays a role in the overall process, and together they show how planning, coordination, and skilled effort turn designs into functional infrastructure.
|
|
|
|
Paint and flags are used to identify existing utilities and future work areas. This helps visualize the work before any excavation starts.
|
|
|
|
|
|
Surface pavement is cut with a large, powered saw. This technique creates a clean, controlled cut to minimize surface disruption and provides access for excavating dirt.
|
|
|
|
|
|
Small holes are dug in advance of the main excavation work to determine the exact location of existing utilities.
|
|
|
|
|
|
A mobile convoy works along the pipeline path. Excavators and dump trucks work in a single file to reduce traffic impacts.
|
|
|
|
|
|
When permissible, steel plates are placed to protect the public during non-working hours.
|
|
|
|
|
|
If steel plates are not permissible, open pits are filled at the end of each day.
|
|
|
|
|
|
At the end of each week, temporary paving will occur in areas that have been disturbed. Crews will return within six months to complete the final paving. Sidewalks and ADA ramps will be restored to their pre-construction conditions.
|
|
|
|
Residents from the Fry's Spring and Johnson Village neighborhoods were invited to attend a virtual meeting on Monday, December 15, 2025, to learn about the upcoming construction efforts. The presentation was divided into two sections: the first focused on RWSA's history and operating metrics, and the second on construction activities on Jefferson Park Avenue and Cleveland Avenue.
|
Central Water Line Project is One of Several Initiatives Planned |
In 2002, the Central Virginia Region experienced a historical drought of record. This drought and the water supply needs of the Charlottesville/Albemarle region sparked a decade-long water supply planning process (2002-2012). Over the next five years, RWSA will invest more than $300 million to enhance our urban raw water storage capabilities, raw water transmission pipelines, treatment facilities, and finished water transmission pipelines (treated drinking water).
|
|
New Earthen Dam – In 2014, RWSA completed building a new dam at the Ragged Mountain Reservoir. Water Treatment Plant Improvements - Recent facility renovations and upgrades have increased treatment capacity. Ragged Mountain Reservoir Pool Fill Project - RWSA will fully utilize the reservoir’s storage capacity by adding 700 million gallons of water for a total capacity of 2.1 billion gallons. Ragged Mountain Reservoir to Observatory Water Treatment Plant Raw Water Line and Pump Station - A new 36” transmission pipe is replacing two smaller 70 and 100-year-old transmission pipes. South Rivanna River Crossing - A large 24” finished water transmission pipe is being added to better support the northern area in Albemarle County. Central Water Line - The Central Water Line will provide a high-flow, large-diameter finished water transmission pipe that will better connect RWSA’s treatment facilities, transmission pipes, water storage tanks, and water distribution piping in the urban area. South Fork Rivanna Reservoir to Ragged Mountain Reservoir Raw Water Pipeline, Pump Station, and Intake - The new pipeline and pump station will allow RWSA to fully utilize the South Fork Rivanna Reservoir’s watershed and Ragged Mountain Reservoir’s storage capacity. It will also allow both water treatment plants to pull water from either reservoir.
|
|
|
|
|