Central Water Line Construction Update

March 2026

As we move into the spring season, we’re pleased to share several updates on the Central Water Line Project.

For those who may be new to this newsletter, welcome! The Central Water Line Project will hydraulically improve the connection between two urban water treatment plants. Once complete, it will add redundancy to the delivery of finished drinking water and enhance overall system reliability. This project represents a significant step forward that will provide both immediate and long-term benefits to our community.
Temporary pavement is installed along Piedmont Avenue. The entire road will be repaved after the installed pipe passes a pressure test. 

Current Construction Efforts

Lewis Street, Price Avenue, Piedmont Avenue, and Stadium Road

Our contractor is currently working on Phase 1, Stage 1, of the project. Pipe installation along Piedmont Avenue is expected to continue for a few more days. Once installation is complete, the newly installed pipe will undergo pressure testing to confirm its integrity and ensure there are no leaks.

This process involves filling the pipe with water and pressurizing it above normal operating pressures for a specified period. If the pipe maintains pressure without any signs of leakage, the contractor will proceed with surface restoration. This includes milling the existing asphalt, repaving the road, and restoring any disturbed concrete.

Advancing to Phase 1, Stage 2 

Jefferson Park Avenue

A picture of a small test pit.
Small holes are dug in advance of the main excavation work to determine the exact location of existing utilities.
The project will soon advance to Phase 1, Stage 2. Following the issuance of a street cut permit from the City late last week, the contractor is preparing to begin work on Jefferson Park Avenue.

Before full excavation for the water line begins, crews will perform exploratory “test holes” to verify the location of existing underground utilities. Although utility owners mark approximate locations with surface paint, these markings must be carefully confirmed in the field by hand digging.
Once utility locations are confirmed, the holes are temporarily backfilled until larger construction operations move through the area. 

The contractor will also sawcut the pavement for the entire length of JPA to create clean edges for the trench work.  This reduces damage to existing pavement outside of the trench line.

Traffic and Parking Impacts

Jefferson Park Avenue

To support saw cutting and test hole operations, temporary changes to traffic patterns and street-side parking will be in place along Jefferson Park Avenue.
Stribling Ave to 
Raymond Ave
Click to enlarge
Raymond Ave to Immanuel Lutheran Church
Click to enlarge
Bi-directional traffic will be maintained; however, southbound traffic south of Robertson Avenue will be shifted into the northbound lane. During active construction hours, on-street parking will be unavailable in affected areas.

These impacts will occur between 9:00 AM and 3:30 PM to minimize disruption during peak commuting times. Normal traffic patterns and street-side parking will resume in the evenings, aside from any construction equipment that remains parked overnight.

Construction activities that do not require traffic lane shifts may occur between 7:00 AM and 6:00 PM.

Door Hangers

We will continue to keep residents informed as construction progresses and additional updates become available. Homes and businesses located directly adjacent to upcoming work areas will receive door hangers, providing notice of anticipated construction activities and any associated impacts. We appreciate your patience and cooperation as we work to complete this important project.

Questions? Feel free to email us at CentralWaterLine@rivanna.org. Want to learn more about the Central Water Line Project?
Visit our construction webpage!

Central Water Line Project is One of Several Initiatives Planned

In 2002, the Central Virginia Region experienced a historical drought of record. This drought and the water supply needs of the Charlottesville/Albemarle region sparked a decade-long water supply planning process (2002-2012). Over the next five years, RWSA will invest more than $300 million to enhance our urban raw water storage capabilities, raw water transmission pipelines, treatment facilities, and finished water transmission pipelines (treated drinking water).
  1. New Earthen Dam – In 2014, RWSA completed building a new dam at the Ragged Mountain Reservoir. 
  2. Water Treatment Plant Improvements - Recent facility renovations and upgrades have increased treatment capacity. 
  3. Ragged Mountain Reservoir Pool Fill Project - RWSA will fully utilize the reservoir’s storage capacity by adding 700 million gallons of water for a total capacity of 2.1 billion gallons. 
  4. Ragged Mountain Reservoir to Observatory Water Treatment Plant Raw Water Line and Pump Station - A new 36” transmission pipe is replacing two smaller 70 and 100-year-old transmission pipes. 
  5. South Rivanna River Crossing - A large 24” finished water transmission pipe is being added to better support the northern area in Albemarle County. 
  6. Central Water Line - The Central Water Line will provide a high-flow, large-diameter finished water transmission pipe that will better connect RWSA’s treatment facilities, transmission pipes, water storage tanks, and water distribution piping in the urban area.  
  7. South Fork Rivanna Reservoir to Ragged Mountain Reservoir Raw Water Pipeline, Pump Station, and Intake - The new pipeline and pump station will allow RWSA to fully utilize the South Fork Rivanna Reservoir’s watershed and Ragged Mountain Reservoir’s storage capacity. It will also allow both water treatment plants to pull water from either reservoir. 